Cagliari's new stadium goes to tender: bids due by 14 January for a 50-year build-and-run concession
By Next News Hub Editorial Team · Published · 2 min read
Cagliari has published its PPP tender for a new stadium on the Sant'Elia site: €212.9m works, a hotel and spa, and offers due 14 January 2027.

After years of drawings, Cagliari's new stadium has entered the phase that usually decides whether an Italian stadium gets built: the contract. On 11 November the City of Cagliari published the tender and the rules for the design, construction and management of the new stadium that will replace the old Sant'Elia. The notice appeared in the EU Official Journal on 12 November and on the national anti-corruption authority's platform on 13 November.
The numbers in the tender
Gara n. 17/2026 is an open procedure for a public-private partnership. The winner will build the stadium and run it under a 50-year concession: the estimated contract period in the EU notice runs from 1 March 2027 to 28 February 2077. The total estimated value of the concession, net of VAT, is about €1.04 billion, a figure that covers the revenues of the whole contract period.
The works themselves are smaller. According to the city's resolution, as reported by La Nuova Sardegna, the stadium costs €212.9 million including VAT. Private capital covers €146.5 million, the Sardinia Region €50 million and the city €16.4 million. Of the city's share, €10 million goes to the detailed design of the demolition, the disposal of the old Sant'Elia and any land remediation, and €6.4 million to contingencies. Another €30.8 million of extraordinary maintenance falls on the concessionaire, taking the investment to €243.8 million.
The project is more than a football ground. It includes a hotel, spa and gym spaces, parking and new outdoor public areas.
How bids will be judged
Bidders have 60 days and can only submit online, through the city's digital platform. The deadline on the ANAC portal is 14 January 2027. The scoring mixes price with quality criteria for works, the design team and, with one of the heaviest weights, the management service: a sign that the city is choosing an operator for half a century, not just a builder.
What comes next
Local press has repeatedly indicated Cagliari Calcio as one of the expected bidders, and the schedule discussed so far points to the demolition of the Sant'Elia and the start of works from March 2027, consistent with the contract start date in the EU notice. Signals suggest the timing is also driven by Euro 2032, which Italy co-hosts with Turkey: Cagliari wants to remain in the running as a host city, and UEFA's checks on candidate stadiums are detailed and demanding.
Key dates
11 November 2026: tender published by the city. 12 November: notice in the EU Official Journal. 14 January 2027: deadline for offers. 1 March 2027: planned start of the concession.